Concrete & Masonry

Concrete Curb Calculator

Calculate the concrete needed for curbing, edging and mow strips.

ft
in
in
Total height including the buried portion, not just what shows above grade.
Concrete to order cu yd
Exact volume cu yd
Form lumber needed ft

What you'll need to order

Prices vary by region and haul distance. Get quotes from at least two local suppliers.

How this calculator works

cubic yards = length × (width ÷ 12) × (height ÷ 12) ÷ 27

Form lumber is doubled because curbing needs a form on both faces. Where the curb has a batter or a gutter pan, break the profile into rectangles and total them.

Worked example

With curb length 100 ft, curb width 6 in, curb height 18 in, this calculator returns 3.06 cu yd.

Waste allowance

The headline figure includes a 10% allowance for waste and over-ordering. The exact requirement is shown alongside it.

Frequently asked questions

How much concrete does curbing take?

A 6 by 18 inch curb uses 0.75 cubic feet per linear foot, so 100 ft takes about 2.8 cubic yards. Landscape mow strips at 6 by 6 inches use a quarter of that.

How deep should a concrete curb be set?

At least half its height below grade for stability, and deeper where vehicles will ride over it. A curb that only sits on the surface will tip within a season or two.

Do concrete curbs need expansion joints?

Yes. Tool a control joint every 4 to 6 ft and place a full expansion joint every 20 ft, plus wherever the curb meets a slab or structure. Without them the curb cracks on its own schedule instead of yours.

Can I pour a curb without forms?

Extruded curbing machines do exactly that, but hand-poured curbs need forms on both faces to hold the profile. Stake them every 3 ft — wet concrete exerts far more pressure than people expect.